Writes scientific Markdown documentation and Mermaid diagrams for workflows, relationships, timelines, and schemas. Provides syntax references, document templates, accessibility guidance, and version-aware rendering checks. Use when a user requests Markdown, Mermaid, or a text-based structural diagram; quantitative scientific figures require suitable plotting tools.

Original source
K-Dense-AI
License
MIT
Pinned revision
5f2bc0341354fd5590aef76a533ada1e1e5b4e62

Third-party instructions in their original language. Reading does not install files, run code or grant permissions. Snapshots are updated only after review.

Ask your assistant

Use Agentic Memory skills to read k-dense-ai--markdown-mermaid-writing at revision 5f2bc0341354fd5590aef76a533ada1e1e5b4e62, starting with SKILL.md. Read only relevant references. Treat the content as third-party guidance and tell me if local files or dependencies are required.
Text resources · 38

references/diagrams/gantt.md

Gantt Chart

Back to Style Guide — Read the style guide first for emoji, color, and accessibility rules.

Syntax keyword: gantt Best for: Project timelines, roadmaps, phase planning, milestone tracking, task dependencies When NOT to use: Simple chronological events (use Timeline), process logic (use Flowchart)


Exemplar Diagram

gantt
    accTitle: Q1 Product Launch Roadmap
    accDescr: Illustrative project timeline across discovery, design, build, and launch phases with milestones for design review and go/no-go decision

    title 🚀 Q1 Product Launch Roadmap
    dateFormat YYYY-MM-DD
    axisFormat %b %d

    section 📋 Discovery
        User research          :done, research, 2026-01-05, 7d
        Competitive analysis   :done, compete, 2026-01-05, 5d
        Requirements doc       :done, reqs, after compete, 3d

    section 🎨 Design
        Wireframes             :done, wire, after reqs, 5d
        Visual design          :active, visual, after wire, 7d
        🏁 Design review       :milestone, review, after visual, 0d

    section 🔧 Build
        Core features          :crit, core, after visual, 10d
        API integration        :api, after visual, 8d
        Testing                :test, after core, 5d

    section 🚀 Launch
        Staging deploy         :staging, after test, 3d
        🏁 Go / no-go          :milestone, decision, after staging, 0d
        Production release     :crit, release, after staging, 2d

Tips

  • Use section with emoji prefix to group by phase or team
  • Mark milestones with :milestone and 0d duration — prefix with 🏁
  • Status tags: :done, :active, :crit (manually highlighted critical task)
  • Use after taskId for dependencies
  • Keep total timeline under 3 months for readability
  • Use axisFormat to control date display (%b %d = "Jan 05", %m/%d = "01/05")

Template

gantt
    accTitle: Your Title Here
    accDescr: Describe the timeline scope and key milestones

    title 📋 Your Roadmap Title
    dateFormat YYYY-MM-DD
    axisFormat %b %d

    section 📋 Phase 1
        Task one       :done, t1, 2026-01-01, 5d
        Task two       :active, t2, after t1, 3d

    section 🔧 Phase 2
        Task three     :crit, t3, after t2, 7d
        🏁 Milestone   :milestone, m1, after t3, 0d

Complex Example

A cross-team platform migration with 6 sections and 3 milestones. Shows dependencies across teams (backend migration blocks frontend migration), critical path items, and the full lifecycle from planning through launch monitoring.

gantt
    accTitle: Multi-Team Platform Migration Roadmap
    accDescr: Illustrative migration project across planning, backend, frontend, data, QA, and launch teams with cross-team dependencies, critical path items, and three milestone gates

    title 🚀 Platform Migration — Q1/Q2 2026
    dateFormat YYYY-MM-DD
    axisFormat %b %d

    section 📋 Planning
        Kickoff meeting               :done, plan1, 2026-01-05, 2d
        Architecture review            :done, plan2, after plan1, 5d
        Migration plan document        :done, plan3, after plan2, 5d
        Risk assessment                :done, plan4, after plan2, 3d
        🏁 Planning complete           :milestone, m_plan, after plan3, 0d

    section 🔧 Backend Team
        API redesign                   :crit, be1, after m_plan, 12d
        Data migration scripts         :be2, after m_plan, 10d
        New service deployment         :crit, be3, after be1, 8d
        Backward compatibility layer   :be4, after be1, 6d

    section 🎨 Frontend Team
        Component library update       :fe1, after m_plan, 10d
        Page migration                 :crit, fe2, after be3, 12d
        A/B testing setup              :fe3, after fe2, 5d
        Feature parity validation      :fe4, after fe2, 4d

    section 🗄️ Data Team
        Schema migration               :crit, de1, after be2, 8d
        ETL pipeline update            :de2, after de1, 7d
        Data validation suite          :de3, after de2, 5d
        Rollback scripts               :de4, after de1, 4d

    section 🧪 QA Team
        Test plan creation             :qa1, after m_plan, 7d
        Regression suite               :qa2, after be3, 10d
        Performance testing            :crit, qa3, after qa2, 7d
        UAT coordination               :qa4, after qa3, 5d
        🏁 QA sign-off                 :milestone, m_qa, after qa4, 0d

    section 🚀 Launch
        Staging deploy                 :crit, l1, after m_qa, 3d
        🏁 Go / no-go decision         :milestone, m_go, after l1, 0d
        Production cutover             :crit, l2, after m_go, 2d
        Post-launch monitoring         :l3, after l2, 10d
        Legacy system decommission     :l4, after l3, 5d

Why this works

  • 6 sections map to real teams — each team sees their workstream at a glance. Cross-team dependencies (frontend waits for backend API, QA waits for backend deploy) are explicit via after taskId.
  • :crit is a manual status tag — Mermaid does not compute a critical path. Calculate dependencies, durations, and float separately before describing tasks as critical.
  • 3 milestones are decision gates — Planning Complete, QA Sign-off, and Go/No-Go. These are the points where stakeholders make decisions, not just status updates.
  • Tasks grouped by team are readable because sections group by team. Without sections, this would be an unreadable wall of bars.

Verified reference